1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts and circumstances of dispositions;

A. The status of the Plaintiff et al. falls under the Plaintiff and the Hyundai Industrial Development Co., Ltd., Hyundai Industrial Development Co., Ltd., NAS Construction Co., Ltd., KS Construction Co., Ltd., Hyundai Construction Co., Ltd., Hyundai Construction Co., Ltd., Hyundai Construction Co., Ltd., Ltd., Taeyoung Construction Co., Ltd., Ltd., Hanyang Global Construction Co., Ltd., Kukdong Construction Co., Ltd., Sindong Construction Co., Ltd., Ltd., Geumdong Construction Co., Ltd., Ltd., Sinhee Construction Co., Ltd., Ltd., Dondong Construction Co., Ltd., Korea Development Co., Ltd., Ltd., Korea Development Co., Ltd., Ltd., Ltd., promotional Co., Ltd., Ltd., and Gak Construction Co., Ltd. (hereinafter “Plaintiff et al.”) under Article 2 subparag. 1 of the Monopoly Regulation and Fair Trade Act (amended by Act No. 1119, Nov. 2, 2011>

(hereinafter referred to as “stock company” is omitted in the name of the Plaintiff, etc.

1) Incheon Urban Railroad 2line Construction Works (hereinafter referred to as the “instant Construction Works”) 1) Incheon Urban Railroad 2

Section 201 Section 201 (hereinafter referred to as the “instant construction sections”) specify the specific construction sections as the construction section number.

) From 216 to 216 sections, the method of design and construction work in package deal with design and construction is divided into 16 sections, and the method of package deal with design and construction work is the method of package deal contract (Turn-Ky) contract in which a package work executor takes charge of both design and construction work, and the ordering person concludes a contract with a single contractor, and the constructor carries out all services, such as financing, purchase of land, design and construction, and operation for construction work, to the ordering person (However, the section 206 section is the method of construction work (the design that reflects the original design presented by the ordering agency at a price lower than the original design).

(c) bidding;

arrow