Text
1. As to KRW 3,445,046,675 among the Plaintiff and KRW 2,129,480,779 among the Plaintiff, the Defendant shall start from August 27, 2015 to March 11, 2016.
Reasons
1. The description of the grounds for the claim shall be as specified in the attached Form;
2. Judgment by public notice of applicable provisions of Acts (Article 208 (3) 3 of the Civil Procedure Act);
3. Some of the rejection parts claim damages with 20% per annum from the next day of the delivery of a copy of the complaint of this case to the day of complete payment. However, the current "Provisions on statutory interest rate under the main sentence of Article 3 (1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings" was enforced from October 1, 2015, which reduces the statutory interest rate from 20% per annum to 15% per annum, and thus, the part exceeding 15% per annum out of the Plaintiff's damages for delay is dismissed as there is no ground.