(영문) 수원지방법원성남지원 2017.11.29 2017가단203885
부당이득금반환 등
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Facts of recognition;

A. On February 25, 2015, the Defendant: (a) determined the use parking lot, garage, and water storage room with respect to the 5,000 square meters of the 46,636 square meters of the land for Goyang-gu, Gyeyang-gu (hereinafter “instant land”); and (b) determined the projected price as KRW 176,60,000 per year; and (c) determined the projected price as KRW 176,600,000

(hereinafter “instant tender”). Of the instant tender notice, the parts related to the instant case are as follows.

1. Granting the right to use a site and granting the right to use a site to the successful bidder in the main tender for construction of a temporary building, structure, vinyl, etc., if it is intended to establish a temporary building, vinyl, etc., the prior report, authorization, and permission shall be obtained from the local government after obtaining the prior approval of the Corporation, and the prior report, authorization, and permission shall be obtained from the local government, and the entry into and exit from the tender site shall be handled by the successful bidder 1) the directions for participation in the tender shall be handled by the successful bidder 4) the purpose of use of this site shall be the garage, parking lot,

(8) Since the site is used by changing its purpose, the permission for use of State property shall be revoked if it is used, the permission for the act in the development restriction zone shall be obtained from the competent authority and used, and shall comply with the competent authority with the inquiry of whether it is possible to grant permission for the use prior to the tender. (9) In using the relevant site, the successful bidder (user) shall adjust the site after undergoing an environmental pollution inspection, etc. on the current filled site.

In such cases, the expenses shall not be claimed from our Corporation.

6. Payment and reversion of bid bonds;

g. The user fee shall be paid by the due date determined by the Seoul Metropolitan Area Headquarters of Korea, and if the user fee is not paid by the due date, the successful bidder shall be cancelled, and the bid bond shall revert to the Corporation, and