(영문) 수원지방법원 2017.09.01 2015가합4781
공사대금
Text

1. The Defendant’s KRW 437,205,901 as well as 6% per annum from May 2, 2013 to September 1, 2017 to the Plaintiff.

Reasons

1. Basic facts

A. The parties concerned are companies engaged in building construction business, engineering work business, housing construction business, etc., and the Defendant is the owner of 2/3 shares among the 7/10 shares, 3 large-scale 44 square meters, and 174 square meters in D large-scale 174 square meters (hereinafter “instant land”) in Suwon-si B large-218 square meters (hereinafter “instant land”).

(b) Standard contract for each contract and construction works completed and completed;

2. Location of the site: Suwon City B.

3. Period: Commencement of construction work, 2011, and completion of construction, 2011.

4. Contract amount: 596,989,800 won (including value-added tax);

6. The time and method of payment of completed portion: To be completed after completion.

7. Warranty period: two years and 11. Other matters after completion: completion shall be within 180 days after the commencement.

Various shares shall be borne by the defendant.

(Expenses for water supply, urban gas, electricity input) installation of household appliances (frigerers, air conditioners, drum laundrys) and attached stuffs in each subparagraph of the office.

C. The Plaintiff bears the cost.

1) On May 2, 2011, the Plaintiff and the Defendant were the land No. 1 and each of the instant land No. 2 (hereinafter “each of the instant buildings”).

In order to build a new building, each of the instant construction works from the Defendant (hereinafter referred to as “each of the instant construction works”) is as follows:

2) Each contract under which the contract is concluded (hereinafter referred to as “each of the instant contract”).

AB concluded the agreement.

Construction Work Standard Contract

2. Site location: Suwon City C.

3. Period: Commencement of construction work, 2011, and completion of construction, 2011.

4. Contract amount: 596,663,100 won (including value-added tax);

6. The time and method of payment of completed portion: To be completed after completion.

7. Warranty period: two years and 11. Other matters after completion: completion shall be within 180 days after the commencement.

Various shares shall be borne by the defendant.

(Expenses for water supply, urban gas, electricity input) installation of household appliances (frigerers, air conditioners, drum laundrys) and attached stuffs in each subparagraph of the office.

C. The Plaintiff bears the cost.

2. The Plaintiff’s instant case.