Text
1. The Defendant shall pay to the Plaintiff KRW 37,00,000 and the interest rate of KRW 15% per annum from October 13, 2015 to the date of full payment.
Reasons
1. Indication of claims: It shall be as shown in attached Form; and
2. Applicable provisions of Acts: Article 208 (3) 1 and Article 257 of the Civil Procedure Act;
3. As the statutory interest rate under the main sentence of Article 3 (1) of the Act on Special Cases concerning Expedition, etc. of Legal Proceedings (the statutory interest rate under the main sentence of Article 3 (1) of the Act on Special Cases concerning Expedition, etc. of Legal Proceedings shall be 15/100 per annum) was amended and promulgated on September 25, 2015 and enforced on October 1, 2015, the part demanding the payment of damages for delay by 20% per annum is dismissed.