(영문) 서울북부지방법원 2018.12.04 2018나44
각서금
Text

1. The defendant's appeal is dismissed.

2. The costs of appeal shall be borne by the Defendant.

Purport of claim and appeal

1...

Reasons

1. The following facts may be found either in dispute between the parties or in Gap evidence 1 (in the absence of a dispute on the part of the defendant's unmanned part, the authenticity of the entire document shall be presumed to have been established), Gap evidence 2 to 5, Eul evidence 1-1, 2, and Eul evidence 2-2, by taking into account the whole purport of the pleadings.

The defendant worked as an employee of the real estate intermediary.

B. On April 28, 2008, the Defendant prepared and delivered each of the following descriptions to the Plaintiff (Evidence A No. 1; hereinafter “instant notes”).

In addition, it promises that the defendant and the head of the department, including the company, will be responsible for securing the principal (C) in the future, if it is impracticable to increase the price for 30 square meters of the land purchased by the D Plaintiff in Pyeongtaek-gun, Gangwon-do.

(B) Principal: 14 million won (one million won) (one million won) on April 28, 2008 by the Defendant (U.S.) Department E (U.D.) of the employee

C. On September 24, 2008, the Plaintiff entered into a contract with F on September 24, 2008, under which approximately KRW 108/5,450 (hereinafter “instant real estate”) out of KRW 5,450,00,00 in Gangwon-gu D Forest land (hereinafter “land before subdivision”) in total, KRW 4,70,000 per square year, and completed the registration of ownership transfer on the instant real estate on September 25, 2008.

At the time of the sale, the officially announced value of the land before the sale was 707 won per square meter.

E. On December 14, 2009, the land before subdivision was divided into the size of 5,152 square meters for D forest land in Pyeongtaek-gun, Gangwon-do (hereinafter “after subdivision”) and the size of 298 square meters for G forest in Gangwon-do. The Korea Electric Power Corporation completed the registration of ownership transfer on December 24, 2009 for G 2929 square meters for land expropriation.

F. On December 7, 2009, the Korea Electric Power Corporation deposited KRW 186,010 for the expropriation compensation with the Plaintiff as a depositee.

G. On December 2, 2013, the Korea Electric Power Corporation: (a) for the land after the subdivision of December 2, 2013, on the ground that the land was used on May 15, 2013, the following: