(영문) 서울행정법원 2016.09.08 2015구합8374
토지수용이의재결처분취소
Text

1. The defendant shall pay KRW 2,016,300 to the plaintiff.

2. The plaintiff's remaining claims are dismissed.

3. Of the costs of lawsuit;

Reasons

- Project approval and public announcement - Project approval and public announcement - Project approval and public announcement - On September 25, 2013 - Project operator - Decision of expropriation by the Central Land Expropriation Committee on November 20, 2014 - Up to 611 square meters (hereinafter referred to as "D"), 50/227 shares (hereinafter referred to as "second-party land"), among the 179 square meters of land, 00 square meters in total, 200 square meters in the land (hereinafter referred to as "each land of this case"), and 200 square meters in the land of this case (hereinafter referred to as "20 square meters in the land of this case"), and 200 square meters in the land of this case: Compensation for losses: 47,608, 90 won in the land of this case (i.e., 46, 270, 250, 253-16, 205).

Therefore, the defendant has not been properly assessed against the plaintiff as to each of the land of this case.

arrow