(영문) 수원지방법원 성남지원 2016.04.21 2015고합237
뇌물수수등
Text

Defendant

A Imprisonment with labor for two years and fines for 25,000,000 won, Defendant B shall be punished by a fine for 2,00,000 won, Defendant C and D, respectively.

Reasons

Punishment of the crime

1. Defendant A, as the captain of the K branch of the Korea-Road Corporation J branch (hereinafter “J branch”), was in charge of the business of purchasing electric facilities and managing and supervising the construction site in relation to the maintenance and repair of electric facilities in the L section managed by the said J branch from January 201 to January 2013 (hereinafter “instant construction”).

A. A. The acceptance of bribe B against B was contracted to KRW 602,477,762 for the instant construction work ordered by the J branch around January 30, 2012 as the representative of M Co., Ltd. (hereinafter “M”).

By taking advantage of the status of managing and supervising the instant construction project, the Defendant, as seen above, intended to accept bribe in return for consideration for the instant construction project’s execution, and received KRW 100,000 from the J Branch’s office located N on February 9, 2012 to B via telephone to transfer “one million won as an employee meeting is required” to B, and received KRW 400,000 from an employee bank account in the name of N-friendly O’s name as of February 10, 2012, with the purport of the same purport, as of March 3, 2012, the Defendant provided the said account with KRW 100,000 to the said account, and KRW 100,000 to the said account on March 14, 2012, and KRW 400,000 as consideration for each of the instant construction projects, such as transfer of KRW 1 million to the said account.

Accordingly, the defendant received a bribe of 400,000 won in relation to the defendant's duties as K staff of J branch.

(2) The acceptance of bribe against D, C, and D are persons running “P” as electrical construction companies.

On November 201, 201, the Defendant received a request from D having a pro rata relationship with the work of this case from B, who was given a contract for the instant construction from the J branch, as described in the above paragraph (1).

arrow