logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 의정부지방법원고양지원 2017.08.16 2016가합1267
공사대금
Text

1. The Defendant (Counterclaim Plaintiff) paid KRW 66,195,063 to the Plaintiff (Counterclaim Defendant) and its related amount from March 31, 2016 to August 16, 2017.

Reasons

1. Facts of recognition;

A. On July 31, 2015, the Plaintiff was awarded a contract for reinforced concrete construction work among the new construction of a Dmju Factory on the ground C at the time of strike by the Multi-Daho Construction Co., Ltd. (hereinafter “Daho Construction”) as KRW 890,000 (excluding value-added tax).

B. On August 20, 2015, the Plaintiff entered into a subcontract with the Defendant (hereinafter “instant subcontract”) with the construction cost of KRW 470,000,000,000 (excluding value-added tax) during the said construction (hereinafter “instant subcontract”), and the terms and conditions of the instant subcontract were as follows.

(2) The parties to the subcontract of this case are not the parties to the subcontract of this case, but the parties to the subcontract of this case who concluded the subcontract of this case with the plaintiff and the parties to the subcontract of this case. However, in full view of the purport of the whole arguments in Gap evidence No. 4, the parties to the subcontract of this case and the defendant representative director's results of the personal examination of the defendant representative director against

4. Hours of construction: Payment of the price for the completion of construction on September 1, 2015, on November 30, 2015;

(b) End portion: (a) Payment method of progress payment for the month according to the construction type ratio within 15 days of the following month: 100 percent in cash;

(1) Payment within 30 days from the date the person placing an order receives a adjustment in accordance with the contents and proportion of such adjustment (2) within 15 days from the date the person placing an order receives such adjustment;

7. Items and quantities of material to be paid: The rate of liquidated damages for delay: 1/1,00 of steel bars and ready-mixed 11. Special Agreement note 1/1,00; 1/1,00 of the Special Agreement note 1) all types of work related to the temporary works (non-establishment, vertical safety net, safety display, etc.) 2) all types of work related to the structural works (including household materials and miscellaneous materials and miscellaneous materials, 3) the subcontractor shall be responsible for any defects in construction; 4) the person responsible for construction shall be stationed at one site.

5 Any balance of the Corporation shall be paid after the shipment of any temporary material.

C. The Plaintiff on February 17, 2016.

arrow