(영문) 대구지방법원 2017.06.09 2016구합23709
사업비 회수처분 취소 청구의 소
Text

1. The Defendant’s disposition to recover project costs against the Plaintiff on November 24, 2016 shall be revoked.

2. The costs of the lawsuit are assessed against the defendant.

Reasons

1. Details of the disposition;

A. On April 30, 2014, the Defendant entered into a contract and entered into a construction agreement with the Plaintiff; on May 7, 2014, the date of commencement; on April 20, 2017, the date of completion; and on April 20, 2017, the construction cost; and on April 5, 002, 857, and 60 won, the “Gangcheon-Yan River Maintenance Project” (hereinafter “instant rearrangement project”).

A) A contract for construction works was entered into on October 20, 201, and the total construction cost was modified to KRW 6,001,608,000 on October 20, 201 through a design change (hereinafter “instant contract”).

(2) Around April 30, 2015, the Plaintiff completed the construction work for piling up stone (hereinafter “instant construction work”) among the construction works under the instant contract, and the Defendant paid the construction cost as to the instant construction work by May 8, 2015.

B. On August 2016, the Gyeong-do’s comprehensive audit and demand for correction was made to the Defendant in 2006, and the Gyeong-do’s comprehensive audit and inspection was made to Ulsan-gun in 2006, and the Gyeong-do’s comprehensive audit and inspection was made to the Defendant, and the Gyeong-do’s request for re-deliberation on the result of the said comprehensive audit and inspection was made. However, on November 1, 2016, the Gyeong-do’s request for re-deliberation should be made based on the method of calculating the construction area of 19,535 square meters, which is excessively calculated as KRW 57,70,000 for the project cost, and the 557,700,000 won for the project cost was excessively executed.

C. On November 24, 2016, the Defendant notified the Plaintiff of the collection and reconstruction of the cost of excess execution with the following content:

(B) Of them, the part ordering excessive recovery of the project cost of the instant rearrangement project (hereinafter “instant disposition”). 【Recovery of the project cost of the instant rearrangement project and notification of reconstruction】

2. Gyeong-do, 2016.