logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 부산지방법원 2015.10.15 2015가단40254
대여금
Text

1. The defendant shall pay 150,000,000 won to the plaintiff and 24% per annum from August 9, 2012 to the day of complete payment.

Reasons

1. The Plaintiff indicated the claim shall pay 150,00,000 won to the Defendant on June 9, 201 at the rate of 24% per annum, which shall be paid on the nine day of each month, and shall be lent to the Defendant at the rate of 150,000,000, which shall not be paid the principal amount and the overdue interest from August 9, 2012, even after the maturity of the payment period. As such, the Defendant is obliged to pay to the Plaintiff delay damages at the rate of 150,000,000 per annum, which shall be the agreement rate of 24% per annum, from August 9, 201

2. Article 208 (3) 3 of the Civil Procedure Act (Judgment by public notice) of the applicable provisions of Acts;

arrow