Text
1. The Defendant’s KRW 81,50,000 as well as the Plaintiff’s annual rate from August 15, 2018 to May 31, 2019, and the following.
Reasons
1. On November 15, 2013, the Defendant awarded a contract for the construction of D Factory site and packing construction (hereinafter “instant construction”) to the Plaintiff on the basis of the cost of KRW 141 million (including value-added tax), the period from November 20, 2013 to February 19, 2014; the construction cost and the period were changed several times at the request of the Plaintiff while the Plaintiff was continuing the instant construction; and the last day on June 10, 2014, the period of construction from June 11, 2014 to July 30, 2014 to the Plaintiff, including the Plaintiff’s evidence Nos. 297 million (hereinafter “instant contract”); and the Plaintiff’s evidence No. 201 to No. 14555, Jul. 14, 2014; and each of the Plaintiff’s evidence No. 2017, evidence No. 1975, Dec. 17, 2014.
According to the above, the Defendant is obligated to pay to the Plaintiff damages for delay under the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings, which is calculated at the rate of 12% per annum from August 15, 2018 to May 31, 2019, after the completion date of the instant construction, as the remainder of the construction cost, excluding the construction cost paid by the Plaintiff from July 21, 2014 to November 21, 2016 by the Plaintiff, among the construction cost under the instant contract, to the Plaintiff, with the remainder of KRW 81.5 million, excluding the construction cost paid by the Defendant from July 21, 2014 to November 21, 2016.
2. Judgment on the defendant's assertion
A. The summary of the instant construction contract states that the construction cost is KRW 297 million, but in fact, the construction cost finally agreed between the original and the Defendant is KRW 235 million agreed on March 10, 2014.
remaining 6.