logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 전주지방법원 2017.11.29 2017가단20298
건물등철거
Text

1. The defendant shall be the plaintiff.

A. The buildings indicated in the attached Form 275 square meters on the land in the Donju-gun of Jeollabuk-do are removed, and the buildings are above.

Reasons

1. The description of the claim is as shown in the annexed sheet of claim.

2. Article 208 (3) 1 of the Civil Procedure Act of the applicable provisions of Acts;

3. Damages for delay calculated at the rate of 15% per annum under the Act on Special Cases concerning the Promotion, etc. of Legal Proceedings for Partial Dismissals may, in principle, be claimed after the delivery of a copy of the complaint, and where the defendant has a substantial objection to the existence and scope of the obligation due to the partial dismissal of the complaint, it may be claimed

arrow