(영문) 대전지방법원 2015.05.28 2013가합8827
소유권이전등기말소등기
Text

1. Defendant E Co., Ltd. is to Defendant C and Defendant D:

(a) in paragraph 1 of the Schedule;

Reasons

1. Basic facts

A. The legal status of the parties (1) (1) the status of the Plaintiff, Defendant C, and Defendant C Co., Ltd. (hereinafter “Defendant C”) (hereinafter “Defendant C”) is the executor of the business that newly constructs and sells A's main apartment complex (the present name is "G,” and refers to "A,” from the following date) on the F on the ground of Daejeon U.S. F., and around May 2003, the Defendant D Co., Ltd (hereinafter “Defendant D”) was selected as the contractor, and entered into a construction contract to contract A's new construction work. The date of the occupancy of each household (the divided building) was set on April 2005.

② The foregoing New Construction Corporation was suspended on July 2004 due to the shortage of business funds between Defendant C and Defendant D, and each household unit A (each partitioned building) held a general meeting on July 24, 2005 to resume the suspended new construction, and established A’s Countermeasures Committee (i.e., the Plaintiff), elected H, I, and J as a joint representative of the Plaintiff, and enacted “Measures Committee Regulations (Evidence 1).”

(2) On July 26, 2005, the Plaintiff entered into an agreement with Defendant C and Defendant D to change the name of the owner of the building A (a collective building) from Defendant C and Defendant D to a person designated by the Plaintiff (hereinafter “instant agreement to change the name of the owner”). On the following day (hereinafter July 27, 2005), the Plaintiff held a general meeting of the buyers A and held the name of the owner of the building, to secure the rights of the buyers A, and the name of the owner was changed to B Co., Ltd. (hereinafter “Defendant B”), the name of which was the representative director at the time I was changed to B Co., Ltd. (hereinafter “Defendant B”), and instead, to preserve the status of the owner of the building under the said agreement to change the name of the owner of the building, the Plaintiff against Defendant C and Defendant D in the name of the Plaintiff.