(영문) 전주지방법원 2017.08.31 2016구합1445
주민사업비 배분결정 무효확인
Text

1. The instant lawsuit shall be dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Details of the disposition;

A. The former Water Supply and Waterworks Installation Act (amended by Act No. 6449, Mar. 28, 2001; hereinafter the same applies) No. 1999-504, Dec. 30, 1999, the Governor of Jeollabuk-do branch office of Jeollabuk-do was designated as the water source protection area of the Busan Dam and the resident support project of this case

(2) Pursuant to Article 5 of the former Enforcement Decree of the Water Supply and Waterworks Installation Act and Article 7 of the former Enforcement Decree of the Water Supply and Waterworks Installation Act (amended by Presidential Decree No. 17381 of Sept. 29, 2001), the area of 17.18m2 per annum of the documents, in the form of the Gu, shall be designated and publicly announced as the area for the protection of the dam from the area of the Gu, and the area of the Gu, shall be designated and publicly announced as the area for the protection of the dam from the area of the Gu. The Plaintiff and the former, in the form of the Gu, shall be designated as the area for the protection of the dam from the area of the Gu, the area of the Gu, in the form of the Gu, the area of the Gu, in the form of the Gu, the area of the Gu, and the area of the Gu, in the form of the Gu, shall be designated as the area of the Gu,

(2) Article 6-2 of the former Water Supply and Waterworks Installation Act of the Republic of Korea provides for a project for the assistance of residents in the water source protection area of the subsidiary dam. However, on December 27, 1999, the Governor of the Jeollabuk-do branch, the defendant, the head of the high-head of the Gun, and the head of the Eup/Myeon Office of the Korea Water Resources Corporation of the Republic of Korea entered into an agreement on the designation of the dam source protection area of the subsidiary dam agreed to implement the project cost of KRW 4 billion (hereinafter referred to as the “instant resident support project”) between the chairperson of the Ansansan Development Committee and the

3. On December 27, 199, the date of publication of the above Convention, from the date of the above publication to the date of December 2001, 200, the subsidiary-gun, which is the managing authority of the resident support project of this case, established the basis for the subject of the support project as to whether a person engaged in agriculture and forestry or fishery in the relevant area actually resided in the subsidiary-dam Dam Protection Area and has difficulty in maintaining his/her main livelihood due to the designation of the water source protection area, who is a person who actually engaged in the agricultural and fishery business in the relevant area,