Text
1. The Defendant (Counterclaim Plaintiff) shall pay to the Plaintiff (Counterclaim Defendant) KRW 111,419,762 as well as the full payment on July 24, 2014.
Reasons
A principal lawsuit and counterclaim shall also be deemed a principal lawsuit and counterclaim.
1. Basic facts
A. The Plaintiff is a company running the construction business, etc., and the Defendant is a company running the lodging business, etc.
B. On June 25, 2013, the Defendant obtained a construction permit from the head of Gwangju Northern District, on the condition that “the construction of the instant building by conducting site boundary surveys, etc. before the commencement of construction shall not cause civil petitions with the neighboring site owners, etc.” with respect to the construction of accommodation facilities on the land located in 12-2, Gwangju Northern-dong (hereinafter “instant building”).
C. On July 13, 2013, the Defendant entered into a contract with the Plaintiff to contract the instant construction of the instant building (hereinafter “instant construction contract”) with the Plaintiff for the construction of the instant building (hereinafter “instant construction contract”). The main contents are as follows.
- The date of commencement: (120 days from the date of commencement): - the contract amount: 855,00,000 won (including value-added tax) on November 15, 2013 - The construction content: “B (the Plaintiff Company; hereinafter the same shall apply)” must perform construction works based on the construction permit conditions and design drawings from the removal and basic civil engineering works; and the construction of “B” shall be made by submitting an unmanned telecom on July 756, 201 as a model at the level of the above unmanned telescope (the outer finishing of the building, the entrance, the entrance, the parking lot, the parking lot, the bus bars, the furniture, the illumination, the lighting room, the kitchen, the guest room, the signboard, etc.) and all other integrated construction works necessary for business to complete the construction project as “the construction of the building and electronic equipment at the request of the Defendant Company,” and “the construction of the building and electronic equipment at the request of the Defendant Company,” as “the construction of the building and the interior equipment necessary for the construction project.”
The Plaintiff started construction works on July 16, 2013 according to the instant construction contract and started existing facilities.