Text
1. The Defendants jointly and severally committed against the Plaintiff KRW 20,438,664 and Defendant A Co., Ltd. from August 11, 2016.
Reasons
1. Indication of claim;
A. On September 17, 2015, the Plaintiff entered into a petroleum products transaction contract with Defendant A Co., Ltd. (hereinafter “Defendant Company”), and Defendant B jointly and severally guaranteed the Defendant Company’s oil payment obligation.
B. The Plaintiff supplied oil to the Defendant Company from September 17, 2015 to November 5, 2015 under the said contract, but the Defendant Company did not pay KRW 20,438,664 for the oil price.
C. Thus, the defendants are jointly and severally liable to pay the above oil price and damages for delay to the plaintiff.
2. Articles 208(3)1 and 257 of the Civil Procedure Act: A judgment without holding any pleadings;