logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 부산고등법원 2020.02.05 2019나53191
대여금
Text

1. Plaintiff 1, among the parts against the Defendant in the judgment of the court of first instance, falls under the following amounts:

Reasons

1. Scope of the judgment of this court;

A. The Plaintiff appears to have agreed on the loan of KRW 50,00,000 as of April 7, 2014 and the agreed on the loan of KRW 50,50,000 (5.5% per annum) or damages for delay (hereinafter “the first claim”), loans of KRW 50,000,000 as of April 7, 2014, and agreed on the agreed interest (7% per annum) or damages for delay (hereinafter “the second claim”), loans of KRW 90,000,000 as of May 7, 2014, and the agreed on the loan of KRW 90,000 or damages for delay (hereinafter “the third claim”), from KRW 70,000 as of May 29, 2014, “the loan of KRW 70,000 or KRW 701,700 as of May 20, 2014,” and “the Plaintiff’s damages for delay” of KRW 701 to 70,714.71.7.

(hereinafter “instant Claim 5”), on October 29, 2014, loans of KRW 50,000,000, and agreed interest thereon (7% per annum) or damages for delay (hereinafter “instant Claim 6”), the court of first instance partly accepted the instant Claim 2 through 6 on May 1, 2019, and rendered a judgment dismissing the instant Claim 1.

On this issue, only the plaintiff appealed against the first claim of this case among the part against the plaintiff in the judgment of the first instance.

B. Meanwhile, at the trial on November 18, 2014, the Plaintiff claimed loans of KRW 40,000,000 and agreed interest thereon (7% per annum) or delay damages (hereinafter “instant claim”) (hereinafter “instant claim”), loans of KRW 20,000,000 as of December 22, 2014, and damages for delay thereof (hereinafter “instant claim”) and the Plaintiff’s claim for the loans of KRW 20,000,000 as of January 8, 2015, and the agreed interest thereon (7% per annum) or delay damages (hereinafter “instant claim”) and the agreed interest thereon (hereinafter “claim 9”), and the loans of KRW 10,000,000 as of March 4, 2015, and any damages for delay.

arrow