Text
1. The plaintiff's claim is dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
Reasons
1. Details of the disposition;
A. On February 4, 2016, the Plaintiff filed a building report, including permission for development and permission for mountainous district conversion, with a view to newly constructing one-story detached houses with a building area of 117 square meters and a total floor area of 9.75 square meters on the 656 square meters (hereinafter “instant application site”) among 2,359 square meters of Kimcheon-si B forest land in Kimcheon-si, Kimcheon-si (hereinafter “instant application site”).
(hereinafter “instant report”). (b)
On March 28, 2016, the Defendant rejected the instant report against the Plaintiff on the following grounds pursuant to Articles 11(5) and 14 of the Building Act, Article 18 of the Mountainous Districts Management Act, and Article 56 of the National Land Planning and Utilization Act (hereinafter “National Land Planning Act”).
(hereinafter referred to as "disposition in this case"). Non-repair of a mountainous district: Permission to convert a mountainous district under Article 18 of the Mountainous Districts Management Act (hereinafter referred to as "permission to convert a mountainous district") is likely to hinder the landscape surrounding the dam due to earth and sand outflow in the course of promoting a project by 787 cubic meters (the cutting 249 cubic meters of the ground, 538 cubic meters of the ground), and there is a concern that C may be located at the lower reaches the water level and the function of preserving water quality of the river when the project is implemented, and there is a concern that there is a concern that there is a concern that there is a concern that there is a possibility that there is a possibility that there are many problems, such as water drainage, surrounding environment, water pollution, etc. adjacent to a dam, and that there is a concern that there is a concern that there is a possibility that there is a change in the form and quality of land within the surrounding area under Article 56 and Article 58 of the National Land Planning and Utilization Act (the permission to convert a mountainous district under Article 58).