1. The defendant's letter of contract for sale in attached Form to the plaintiffs as to each of the following money and each of the above money.
Reasons
1. Basic facts
A. The Defendant is the executor of the business that newly constructs and sells the 7th underground floor, the 18th ground floor, and the 664 households of the 664-households on the ground of Silung-si (hereinafter “instant officetels”).
B. The Plaintiffs concluded a sales contract with the Defendant for some households of the instant officetel as indicated in the attached Form sales contract list (hereinafter “each sales contract of this case”).
The contents of each sales contract of this case related to this case are as follows.
(1) The term "A" in the following contents means the defendant who is an executor, and the term "B" means the plaintiffs who are several buyers: The scheduled occupancy date: January 2018 (the scheduled occupancy date after approval for use may be changed according to the process, and the accurate occupancy date may later be notified) "A" in Article 1 (1) of the 2018 shall be completed and sold to "B", and "B" shall pay the supply price in accordance with the provisions of Article 2.
Article 10 (Cancellation of Contracts) (4) "B" may cancel this contract where it is impossible to move into within three months from the scheduled date of occupancy due to the reasons attributable to "A".
(Provided, That if the occupancy is delayed due to force majeure, such as an administrative order, which is unrelated to the cause attributable to A, a natural disaster, or an administrative order, etc., which is not related to the cause attributable to B, the “B” shall not be required to cancel the contract. Article 11 (Penalty and Refund) (2) When the contract is terminated due to a cause falling under Article 10(4), the “A” shall be paid to “B” as a penalty.
C. The Plaintiffs paid the down payment and intermediate payment to the Defendant in accordance with each of the instant sales contracts.
When the completion of the instant officetel was delayed, the Plaintiffs sent to the Defendant a certificate of content that “each of the instant sales contracts shall be rescinded pursuant to Article 10(4) of the instant sales contract between April 30, 2018 and May 25, 2018.”
Each of the above.