logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 광주지방법원순천지원 2017.12.07 2017가합12005
채무부존재확인
Text

1. The Plaintiff’s Defendant based on the standard contract for private construction works concluded on March 3, 2016 between the Plaintiff and the Defendant.

Reasons

1. Basic facts (applicable for recognition: non-strifeed facts, Gap evidence 1 through 7 (including paper numbers, hereinafter the same shall apply);

(2) Each entry and the purport of the whole pleading

A. On March 3, 2016, the Plaintiff entered into a contract with the Defendant for the construction of a new house on the ground (hereinafter “instant construction”) to contract the construction cost of KRW 220,000,000, and the construction period from March 7, 2016 to June 15, 2016 (hereinafter “instant contract”). After that, while performing the instant construction, the retaining wall construction was added to the retaining wall construction and the additional costs, such as roof finishing construction, and heat cutting, were incurred.

The fake gold amount on March 7, 2016. 66,00,000,000 on September 12, 2016, 2016. 66,00,000,000 April 29, 2016. 5,000,000 on April 4, 2016, 200 on May 19, 2016. 20,000,00 on May 20, 200,00 on May 18, 200,00 on June 22, 200,000 on June 16, 200, 200,000 on September 5, 200, 2000,00000;

B. The Plaintiff paid the Defendant a total of KRW 207,00,000 as follows.

(F) The amount of fake gold D (C) No. 10,000,000 on April 22, 2016, 2016, May 9, 2016, 2016, in the case of the mutual savings bank for the settlement of accounts (Co., Ltd.) No. 10,500,000 on April 22, 2016, 2016, July 4, 2016; 1,706,000 E (TM) on July 4, 2016; 47,206,0000 on August 5, 2016, 200,0000 on aggregate of 47,206,000

C. Upon the Defendant’s request relating to the instant construction project, the Plaintiff paid the subcontractor a total of KRW 47,206,00 as follows:

During the construction of this case, the Plaintiff directly performed gas pipes, rainets, gates, and railing construction, and disbursed the total of KRW 4,593,650 (=2,685,650 for the cost of installing gas pipes in the amount of KRW 598,00 for the cost of installing Bashing KRW 260,000 for the cost of installing Bashing KRW 260,000 for the cost of installing Bashing KRW 260,000 for the cost of installing Bashing KRW 2,685,650)

E. The Plaintiff filed a payment order against the Plaintiff by asserting that the Plaintiff acquired KRW 11 million of the construction price in this case from the Defendant, but the Plaintiff filed an objection on June 20, 2017 and continues to file a lawsuit.

(2017 Ghana5608). 2. Claims and judgments

A. The defendant asserts.

arrow