1. The Defendant’s KRW 56,879,804 as well as the Plaintiff’s annual rate from December 16, 2014 to September 15, 2017.

Reasons

1. Occurrence of liability for damages;

A. At around 03:00 on December 16, 2014, B: (a) a taxi for business use C (hereinafter “Defendant vehicle”).

2) On the other hand, on the other hand, the Plaintiff was at the same time at the right end of the Defendant’s vehicle, and was at the same time at the same time at the same time at the same time at the same time at the same time at the same time at the same time at the same time at the 73 lane of the scopic scopic scopic scopic scopic scopic scopic scopic scopic scopic scopic scop

(2) The Defendant is a mutual aid business operator who entered into a motor vehicle mutual aid contract for the Defendant’s vehicle.

[Ground of recognition] Facts without dispute, Gap 1, 2, 5, 6 evidence, Eul 3 evidence (including each number; hereinafter the same shall apply), the purport of the whole pleadings

B. According to the facts of recognition of liability, the defendant is liable to compensate the plaintiff for the damages caused by the accident in this case as a mutual aid business operator of defendant vehicle.

C. However, according to each of the above evidence, the plaintiff, as well as the plaintiff, was involved in the accident of this case while walking along the inside of the roadway at night. Since the plaintiff's above negligence also caused the above accident, the plaintiff's liability is limited to 75% of the damage suffered by the defendant, taking this into account.

2. In addition to the matters stated below within the scope of liability for damages, each corresponding item of the Schedule of Calculation of Compensation for Damages shall be as follows, and in principle, the period for the convenience of calculation shall be calculated on a monthly basis, but less than the last month and less than KRW 1 shall be discarded.

The calculation of the current value at the time of the accident shall be based on the reduction rate of 5/12 percent per month to deduct the interim interest.

In addition, it is rejected that the parties' arguments are not stated separately.

Personal information 1) Personal information: as stated in the “basic matters” list of damages calculation sheet: income and operating period: urban daily wage, number of operating days until the age of 60).