1. The Defendant: (a) KRW 248,541,700 for the Plaintiff and KRW 5% per annum from October 21, 2017 to April 17, 2018; and (b) the Plaintiff.

Reasons

1. Details of ruling;

(a) Project approval and public announcement - Project name: B housing redevelopment and rearrangement project - Project implementer: Defendant - A public announcement of project approval: Eunpyeong-gu Seoul Metropolitan Government on September 15, 2011;

B. On August 25, 2017, the Plaintiff filed the instant lawsuit immediately without filing an objection with the Central Land Expropriation Committee regarding the said adjudication on expropriation.

- Subject to confinement: Each of the following sections owned by the plaintiff (hereinafter referred to as "each of the above sections" and "each of the above sections" are a sectioned building, and the share of the site was evaluated as a unit of sectional ownership of the building:

(1) The Eunpyeong-gu Seoul Metropolitan Government No. 1 E, 1st floor F, 2nd floor G, 2nd floor H, 3rd floor J, 4th floor K, 4th floor L, and 9th floor E, 1st floor F, 1st floor N, 1st floor N, 2nd floor G, 2nd floor H (in the case of a unit of the above unit of 1/5 shares, the remaining 4/5 shares were owned by NonpartyW), 3rd floor I, 3rd floor J, 4th class H, 4th class P, 4th class P, 4th class Q, 5th class H, 4th class K, and 4th class H, 4th class H, 4th class H, and 4th class (2nd class M, 4th class H, 4th class H, 4th class M, and 9th class M, and 9th class M, 200, 360, additional 105th class 5th class 1.

2. The assertion and judgment

A. 1) The Plaintiff’s assertion ①, 2) seek payment of money equivalent to the difference between the reasonable amount of compensation according to the court’s appraisal result and the amount of compensation for expropriation decision as to each partitioned building. In addition, according to the increase of compensation as above, the Act on Acquisition of and Compensation for Land, etc. for Public Works Projects (hereinafter “Land Compensation Act”).

The late payment penalty stipulated in Paragraph 3 of Article 30 shall also be paid.