(영문) 부산지방법원 2017.12.20 2016가합40692
손해배상(기)
Text

1. The defendant,

A. The amount of KRW 15 million to Plaintiff A, KRW 1 million to Plaintiff B, and KRW 500,000 to Plaintiff C, D, and E respectively.

Reasons

1. Basic facts

A. The relation 1) The defendant was established on August 16, 1974 by designating the trade name as "L Co., Ltd." and changed the trade name to "K Co., Ltd." on February 20, 2006, and around March 3, 1978, as a factory producing asbestos products to Busan M (hereinafter "the asbestos plant of this case").

2) Plaintiff A newly built asbestos bags and changed from December 7, 1978 to January 17, 1979, to another type of business. From July 8, 1980 to October 24, 1980, Plaintiff A resided in the Dong-dong (around 1.4 km in the street with the above factory) of the same Gu from July 8, 1980 to October 24, 1980, from P (around 1.2 km in the street with the above factory), from October 24, 1980 to June 16, 2003, Plaintiff B resided in the same Gu Q (a 1.2 km in the street with the above factory) of the same Gu. Plaintiff CD and Plaintiff CD of the same Dong-dong from July 8, 1980 to October 24, 1980 to June 16, 2003.

3) From Sep. 10, 1993 to Oct. 24, 201, Plaintiff F resided in 111 (around 960 meters in the street with the above factory) of the building Rgu in Busan (around 1993 to Oct. 24, 201) and Plaintiff G is the wife of Plaintiff F, and Plaintiff H, I, and J are the children of Plaintiff F. B. The status of the asbestos plant in this case was 14 employees of less than 30 employees, most of the asbestos storage plant in Korea was located in Busan, and more than 9, more than 2 employees of Busan, and more than 14 employees were located in Busan, and more than 10 employees were located in Korea. The asbestos storage plant in this case was the largest of 2nd factories from Busan to 2nd, and more than 10 employees from Feb. 1998.

2 The asbestos plant inside the asbestos plant in this case is not installed in all processes, and even if part of the facilities are installed, the asbestos dust in a state where the work is not properly operated, and the asbestos dust in the work has been continuously generated.