(영문) 춘천지방법원강릉지원 2017.07.20 2017구합30062
관광사업계획 변경승인신청 반려처분 취소
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Details of the disposition;

A. As to the business of expanding accommodation facilities (a) in respect of the land and buildings on the land (hereinafter referred to as “instant real estate,” the land and buildings on which 47-4 and eight parcels of land (hereinafter referred to as “the instant building”) are located in Yangyang-gun, Yangyang-gun, Yangyang-gun, Yangyang-gun, Yangyang-gun, Yangyang-gun, Yangyang-gun, Yangyang-gun, Yangyang-gun, Yangyang-gun, Yangyang-gun, Yangyang-gun, Yangyang-gun, Yangyang-gun, Yangyang-gun, Yangyang-gun, Yangyang-gun, Yangyang-

On August 13, 2007, the non-party company obtained a building permit from the defendant to convert the purpose of the building of this case into accommodation facilities (responding condominiums) and extend the building.

B. Around July 31, 2009, Nonparty Company submitted a report on the commencement of construction to the Defendant and started construction of the instant building at that time. However, the Plaintiff was awarded a successful bid on June 2, 2014 in the public sale procedure with respect to the instant real estate and acquired the ownership of the instant real estate during several years after the construction was suspended while only a part of the construction was being performed.

C. Around July 2014, the Plaintiff filed an application with the Defendant for revocation of the above construction permit, but the Defendant rejected it. Accordingly, the Plaintiff filed a lawsuit for revocation of the said construction permit under the jurisdiction of Gangseo-gu District Court 2015Guhap1565, and received a favorable judgment. The judgment became final and conclusive, and the Defendant revoked the said construction permit on February 26, 2016.

On the other hand, the Plaintiff reported to the Defendant on March 2016, but the Defendant refused to accept the instant business plan. Accordingly, the Plaintiff filed a lawsuit for revocation of a disposition for revocation of succession to the status of a tourism business operator by Gangseo-gu District Court 2016Guhap50236, and received a favorable judgment. The judgment became final and conclusive, and the Defendant accepted the Plaintiff’s report on the above succession to the status on September 13, 2016.

(e).