(영문) 대전지방법원 2016.12.23 2016가합53
공사대금
Text

1. The Defendant shall pay to the Plaintiff KRW 206,201,110 and the interest rate of KRW 15% per annum from January 20, 2016 to the date of full payment.

Reasons

1. Basic facts

A. On July 10, 2015, the Plaintiff entered into a contract for three construction contracts between the Plaintiff and the Defendant. On July 10, 2015, the contract amount of KRW 165,851,450 (including value added taxes; hereinafter the same shall apply) with respect to the creative and steel works among the new urban residential housing construction works contracted by the Defendant for the Daejeon A.

(2) As to the construction period from July 10, 2015 to October 20, 2015, the subcontract was concluded (hereinafter “instant first contract”).

(2) On October 19, 2015, the Plaintiff entered into a contract with the Defendant on July 10, 2015 to November 25, 2015, the contract price of the said contract was KRW 184,701,10, and the construction period was changed from July 10, 2015 to November 25, 2015. (2) On August 10, 2015, the Plaintiff entered into a subcontract agreement with the Defendant on April 2, 2015, with respect to the extension work of Daejeon, Daejeon, C’s reinforced concrete concrete roof 6 stories, and Class 1 and 2 neighborhood living facilities (hereinafter “instant building”); the construction period of KRW 10,00,000,00,00, and KRW 15,000,000 and KRW 25,05,000,000 and KRW 15,05,05,000,00. 3,05,00. 20. 3,00.

(B) The Plaintiff and the Defendant agreed to the effect that the total contract amount of the instant secondary contract was reduced to KRW 126,50,000 (= KRW 110,000,000 - KRW 16,753,000 - KRW 235,00) after the completion of these subcontractings.

3. On December 2015, the Plaintiff entered into a third contract with the Defendant, Daejeon Seocheon-dong, the Defendant received a contract.