Text
1. The Defendant shall pay to the Plaintiff KRW 114,441,200 and the interest rate of KRW 15% per annum from December 26, 2018 to the date of full payment.
Reasons
1. Indication of claim;
A. The Plaintiff is a company that manufactures and sells concrete products, etc., and the Defendant is a person who runs the construction business under the trade name of “D” in the racing-si.
B. On April 14, 2016, the Defendant ordered the Plaintiff to “a reinforced retaining wall construction” among “a building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building building
C. The Plaintiff continued construction until August 10, 2017, and the Defendant paid only part of the construction price to the Plaintiff, and did not pay KRW 114,441,200.
Accordingly, the payment of the unpaid construction cost and the damages for delay under the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings shall be claimed from the next day.
2. Judgment by service (Article 208 (3) 3 of the Civil Procedure Act).