(영문) 대구지방법원서부지원 2020.12.17 2019가합51974
물품대금
Text

Defendant B shall pay to the Plaintiff KRW 370,042,818 as well as 12% per annum from August 22, 2020 to the day of full payment.

Reasons

1. Claim against the defendant B

A. The Plaintiff is a company that manufactures and sells textile products. Defendant B is a person who manufactures and sells textile products with the trade name “D.” 2) The Plaintiff has been supplying the raw materials of textile products to Defendant B prior to the conversion into a corporation. On January 28, 2015, the Plaintiff supplied Defendant B with the goods equivalent to KRW 41,820,049, which was after the conversion into a corporation, and continuously traded goods with Defendant B until May 2, 2019.

However, as of May 2, 2019, the amount payable by Defendant B is KRW 370,042,818.

3) Therefore, Defendant B is obligated to pay to the Plaintiff the amount of KRW 370,042,818 of the above goods and damages for delay calculated at the rate of 12% per annum under the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings from the day following the day when the copy of the application for the change of claim and the cause of claim was served on the Plaintiff on August 14, 2020 to the day when the copy of the application was served on the Plaintiff. (B) As the applicable provisions of Article 208(3)2 and Article 150(3) of the Civil Procedure Act (a) of the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings (around 14, 2020, Defendant B was absent from all on the date of pleading after receiving a written answer

A. Basic facts 1) The Plaintiff, a company that manufactures and sells textile textile products, supplied the textile product raw materials to Defendant B, which is engaged in the textile manufacturing business under the trade name of “D”. As of May 2, 2019, the Plaintiff was not paid KRW 370,042,818 out of the price of the goods traded with Defendant B. (2) As of February 24, 1999, Defendant C, the spouse of Defendant B, completed the registration of ownership transfer for each of the lands listed in the separate sheet Nos. 1 through 3 as of February 11, 199.

After Defendant C newly constructed a building listed in paragraph 4 of the attached list on each land listed in the attached list Nos. 1 and 2, Defendant C completed registration of preservation of ownership on August 10, 199.

Attached List 1.3