(영문) 서울중앙지방법원 2017.08.11 2016가단5282373
손해배상(자)
Text

1. The Defendant’s KRW 129,844,560 for the Plaintiff and KRW 5% per annum from January 29, 2013 to August 11, 2017.

Reasons

1. Occurrence of liability for damages;

A. Facts of recognition 1) B-si (hereinafter “Defendant vehicle”);

() On January 29, 2013, the driver drivened the Defendant’s vehicle on the left-hand side of the Defendant’s vehicle, and proceeded with the 663 Dogdo of Jindo-gun, Jindo-do to the front-do area of the Jindo-gun’s Dog-do, Jindo-gun’s Dogdo from the Dogdogdog-ri, Dogdo-do, in order to overtake the front-do cargo vehicle, the driver pusheded the central line, while driving the Defendant’s vehicle on the left-hand side of the Defendant’s vehicle (hereinafter “instant accident”).

2) According to the instant accident, the Plaintiff suffered injury, such as the lower part of the Hashesium, the upper part of the Hashesium, the upper part of the Hashesium, and the Hashesium, etc.

3) The Defendant is a mutual aid business entity that has entered into a mutual aid agreement on the Defendant’s vehicle. According to the fact of recognition of liability, the Defendant is responsible for compensating the Plaintiff for the damages caused by the instant accident as a mutual aid business entity for the Defendant’s vehicle. [Grounds for recognition] In the absence of dispute, A 2, 3, 5, and 6 (including a serial number, the purport of the entire

2. In addition to the matters stated below within the scope of liability for damages, each corresponding item of the Schedule of Calculation of Compensation for Damages shall be as follows, and in principle, the period for the convenience of calculation shall be calculated on a monthly basis, but less than the last month and less than KRW 1 shall be discarded.

The calculation of the current value at the time of the accident shall be based on the reduction rate of 5/12 percent per month to deduct the interim interest.

In addition, it is rejected that the parties' arguments are not stated separately.

Personal information 1) Personal information: Standard income and operating period in the annexed sheet for calculation of damages amount: 2) The daily wage for male community, the number of working days per month, and 3 years from the date of the accident in this case, the Plaintiff was engaged in agriculture while working as a building tree at the time of the accident in this case. As such, the average monthly income of KRW 2,531,804 as a type of building mold = 115,082 per day of the type of mold x 115,082.