logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 인천지방법원 부천지원 2017.01.13 2016가단22679
대여금
Text

1. The Defendants are jointly and severally liable to the Plaintiff for 26,00,000 won and the period from July 1, 2010 to December 10, 2016.

Reasons

1. The description of the grounds for the claim shall be as specified in the attached Form;

2. Article 208 (3) 3 of the Civil Procedure Act (Judgment by public notice) of the applicable provisions of Acts;

3. The Plaintiff seeking payment of interest or delay damages calculated at the rate of 15% per annum from December 23, 2009, the date of issuance of a promissory note, but there is no evidence to prove that the due date of the payment of the promissory note was June 30, 2010, and there is no other interest agreement until the due date. Thus, the Plaintiff’s assertion seeking payment of interest from December 23, 2009 to June 30, 2010 is without merit, and there is no evidence to acknowledge the agreement to pay delay damages calculated at the rate of 15% per annum from July 1, 2010, the next day to December 10, 2016, which is the delivery date of a copy of the complaint of this case. Thus, there is no evidence to acknowledge the agreement to pay delay damages calculated at the rate of 5% per annum as stipulated in the Civil Act.

arrow