Text
The defendant shall pay 60,00,000 won to the plaintiff and 12% per annum from July 15, 2020 to the day of complete payment.
Reasons
1. Facts of recognition;
A. On December 26, 2018, the Plaintiff was awarded a subcontract by the Defendant for the construction cost of 154,000,000 won (including value added tax) and the construction period of 10 February 10, 2019 among the new construction works of neighborhood living facilities at the Ulsan-gu Seoul Central District Court (hereinafter “instant construction works”).
B. The Plaintiff completed the instant construction by February 10, 2019, and was paid KRW 44 million from the Defendant on January 8, 2019, and KRW 44 million on January 31, 2019.
[Ground of recognition] Facts without dispute, entry or video of evidence A 1 to 5, the purport of the whole pleadings
2. According to the above facts finding as to the cause of the claim, the defendant is obligated to pay to the plaintiff delayed damages calculated by the ratio of 12% per annum from July 15, 2020 to the day of complete payment as stipulated in the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings, etc., as requested by the plaintiff, to the plaintiff, except in extenuating circumstances.
3. In conclusion, the plaintiff's claim of this case is justified and it is so decided as per Disposition.