(영문) 광주지방법원 2013.12.10 2013가단5423
채무부존재확인
Text

1. With respect to the damages described in Paragraph 2 of the above list caused by the accidents described in paragraph 1 of the attached list, the Plaintiffs.

Reasons

1. The following facts are not disputed between the parties, or each of the following facts can be acknowledged by taking into account the following facts: Gap evidence 1, Gap evidence 2, Eul evidence 5, Eul evidence 6-1, 2, 3, Eul evidence 6-2-1, 2, 3, and 4-2-3, part of Gap evidence 3 (excluding the part that is hard to be trusted in the future) and the fact-finding results on the Incheon Institute Co., Ltd. for the Incheon Institute for the Development of the Republic of Korea; contrary thereto, Gap evidence 4-2, Gap evidence 3, 4-1, and part of Gap evidence 4-2, Gap evidence 4-1, Eul evidence 5, Eul evidence 6-2-1, Eul evidence 2-2, Eul evidence 3, and the result of the fact-finding by the plaintiff Party B

Plaintiff

A mutually named “C” owns D 25t mid-term season (hereinafter “instant mid-term season”) as an individual entrepreneur who engages in construction machinery leasing and contracting business.

Plaintiff

B is a "C" driver of an aircraft employed by the plaintiff A.

B. On July 4, 2012, the Defendant concluded a contract with the Plaintiff A and the Plaintiff B, a driver affiliated with the Plaintiff, on July 5, 2012, to lease KRW 600,000,00 for the purpose of the reinforcement of the construction as a drainage of the Incheon Seo-dong 336, Seowon-dong, Seowon-dong, Incheon, Seowon-dong, Incheon, which was subcontracted by the Defendant from the ASEAN Construction Co., Ltd.

C. On July 5, 2012, Plaintiff B arrived at the work site of the Incheon Fire Institute Work on 07:45, the Incheon Fire Institute Work site, along with the instant devices, and participated in the site descriptions from the Defendant’s employees E, along with the site descriptions.

Plaintiff

B At the same time, in order to drive and re-establish the heavy water tank (4.2m x 1.8m x 5.0m x 5.0m) of the instant heavy season, which was carried in from outside at the time and was in the work site for truck, the Defendant’s employees E et al. used a boom for the boom of the instant heavy season at the right time. For this reason, the high voltage power transmission line is interrupted by passing through the high voltage power transmission line in the vicinity of the instant heavy season and the development period of the said Incheon EF Headquarters is suspended.