Text
1. The Defendants jointly share KRW 47,506,520 with respect to the Plaintiff and KRW 5% per annum from July 9, 2016 to October 4, 2018.
Reasons
Facts of recognition
The Plaintiff is a company that operates agricultural and fishery products distribution business, etc., and Defendant B is an individual who is engaged in freezing and refrigerating equipment manufacturing business in the trade name of “E.”
Defendant C is a company that operates the heat resistant manufacturing business, and Defendant D is a person who establishes and repairs a heat resistant system in the name of F.
On January 16, 2015, the Plaintiff entered into a contract for construction with Defendant B for the following construction works, including the conclusion of a contract for construction.
(hereinafter referred to as the “instant construction contract”). The name of the construction project: G (hereinafter referred to as the “instant freezing storage”): 310,000,000 (Additional Tax Separate Construction Period): Article 8 (1) of the Act from January 14, 2015 to February 15, 2015 (the completion of construction works) (Defendant B) (i) shall, upon completion of the contracted construction, remove the construction facilities, surplus materials, wastes, temporary materials, etc. from the construction site; and (ii) all losses incurred before the completion of the construction shall be paid in full, except in the case of natural disasters or force majeure.
On March 25, 2015, Defendant B entered into a subcontract with Defendant C for the heat change of the underground heat control of the freezing storage underground floor of this case (hereinafter “the heating control construction of this case”) at KRW 7,700,000,000, and Defendant C accordingly supplied the Defendant B with four heat control units, and entrusted Defendant C with the installation work.
Defendant D, around 18:00 on July 2, 2015, when the fire occurred and the fire occurred, he used fire extinguishers, water, etc. to extinguish part of the fire.
Since then, Defendant D thought that the postponement from the above timber completely disappearedd from all the scargs, and left the above site without confirming whether the fire site is completely scarged, and he is living again.