(영문) 서울북부지방법원 2018.09.05 2017가단25717
노임 등
Text

1. The claim of this case is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. The parties' assertion

A. The Plaintiff was awarded a subcontract for the construction of the F apartment collapse risk zone in Gwangju-gu E from the head of the Defendant’s site office D and completed the construction work, and the Defendant is obligated to pay the Plaintiff wages and material cost of 32,358,280 won and delay damages.

B. The Plaintiff did not have subcontracted the construction from the Defendant or invested expenses at the construction site of the Defendant.

2. Each evidence submitted by the Plaintiff alone was subcontracted to the Plaintiff’s assertion from the Defendant.

It is not sufficient to recognize that expenses have been paid at the construction site of the defendant, and there is no other evidence to acknowledge it.

The plaintiff's above assertion is without merit.

3. In conclusion, the claim of this case is dismissed as it is without merit. It is so decided as per Disposition.

arrow