logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울중앙지방법원 2016.02.03 2014가단5253128
손해배상(기)
Text

1. The plaintiffs' claims are dismissed.

2. The costs of lawsuit are assessed against the plaintiffs.

Reasons

1. Basic facts

A. New Daily Co., Ltd. (hereinafter “New Daily”) planned the apartment development project that constructs 24 square and 34 square and 512 apartment units on the land in Yeongdeungpo-gu Seoul Metropolitan Government J (hereinafter “instant project site”) (hereinafter “the instant project site”), and established a regional housing association that covers the instant project site, and sought a method of being selected as an enforcement agent from the regional housing association, and prepared to establish a regional housing association on the ground of K. From the end of 2001, K prepared to establish a regional housing association on the ground of the instant project site, referring to as “from the end of 2001 as the head of the association with the head of the regional housing association having the head of the association as the head of the association, and prepared for the construction of the city.”

B. On April 30, 2003, K entered into a contract with L District Housing Association (not having obtained authorization to establish a new housing association until the time) to carry out the instant project in the instant project site on behalf of a contractor, a contractor, a contractor, a contractor, and a public-private housing construction contract with the Central Construction Corporation (hereinafter “Central Construction”) to carry out the instant project on behalf of a contractor (the recommendation work of a construction company, etc., related to housing purchase and sale, association members, association-related work, authorization and permission work, contract work, contract work, completion and settlement work). On June 21, 2003, K entered into a contract with L District Housing Association as a contractor, a contractor, a contractor, and a central construction.

C. During the period from June 22, 2004 to December 20, 205, the Plaintiffs entered into a housing association with the aim of paying KRW 250 million (24 square meters) or KRW 285 million (32 square meters) to the association members’ contributions between the implementation company’s regional housing association, the agency construction company’s new construction company, and the central construction company, and receiving some of the contributions from the National Bank under the joint and several guarantee of the central construction.

arrow