Text
1. The defendant against the plaintiffs as to the money stated in the "request amount" column and each of the above money in the separate claim list.
Reasons
1. In the case of entry of the lot number below the E-dong number in the 1A, the transfer date of ownership transfer (won) for the change of the administrative district in the land to be acquired by the owner of the basic fact-finding No. 1, the “top
F on November 14, 2003, G 149,145,000 square meters G 1478 square meters prior to H on November 14, 2003, J 10,560 square meters K 10,560,000 J 14 November 14, 2003, M 85,880,000 square meters prior to L on December 2 B on December 14, 2003 85,880,0000 square meters on December 3, 2003, CN 158 square meters 23,305,000,0000 P 86 square meters and Q 12,685,000 square meters prior to October 25, 2003, 2003, 305 square meters, 205,38,45,205 square meters and/or 45,2005 square meters;
In around 2003, the Defendant paid each corresponding price to the Plaintiffs under the former Act on the Acquisition of Land, etc. for Public Works and the Compensation therefor (amended by Act No. 8665 of Oct. 17, 2007; hereinafter “Public Works Act”) for the D Road Construction Project (hereinafter “instant road project”), and acquired through consultation each relevant land indicated in the column for “acquisition land” in the table below from the Plaintiffs (hereinafter “each of the instant lands”). The registration of ownership transfer for each of the above lands was completed on each corresponding date indicated in the table “transfer date of ownership” as follows.
Each of the instant lands was modified as indicated in the “administrative district change” column below due to the change of administrative district.
(hereinafter referred to as the “acquisition land”). B.
On December 30, 2005, the Minister of Construction and Transportation, including each of the instant lands on December 30, 2005, designated the housing site development area (public notice AB of the Ministry of Construction and Transportation), the president of the Korea National Housing Corporation, as the implementer of the housing site development project (hereinafter “instant housing site development project”).
On May 2, 2008, the Governor of Chungcheongbuk-do approved and publicly announced a development plan for the housing site development project of this case (Public Notice AC of Chungcheongbuk-do), and on January 8, 2013, the implementation plan for the housing site development project of this case.