(영문) 대구지방법원 2019.11.21 2019고단4578
배임수재
Text

Defendant

A shall be punished by imprisonment with prison labor for eight months and by imprisonment for four months.

, however, from the date this judgment becomes final.

Reasons

Punishment of the crime

[Criminal Power] On July 4, 2019, Defendant B was sentenced to a suspended sentence of two years in the period of eight months for the crime of giving property in breach of trust at the Daegu District Court, which became final and conclusive on July 12, 2019.

【Criminal Facts】

1. Defendant A entered into the Steel Manufacturing Co., Ltd. Co., Ltd in Nam-gu, Nam-gu, Nam-gu, Seoul, around March 1976 and works as the director of the Steel Manufacturing Co., Ltd. from April 201 to September 2018. Defendant A is a person in charge of technical assistance, supervision, etc. of processing facility construction, who is divided into upper temperature or nearby temperature without heating any cooling equipment metal ordered by the Dispute Settlement Co., Ltd.

In January 2015, the Defendant received money of KRW 48,00,000 in total six times from January 2015 to December 2016, 2016, from the representative of the Dispute Resolution Co., Ltd. Co., Ltd., a member of the Dispute Resolution Co., Ltd., a member of the Dispute Resolution Co., Ltd., a member of the Dispute Resolution Co., Ltd., a member of the Dispute Resolution Co., Ltd., a member of the Dispute Resolution Co., Ltd., a member of the Dispute Resolution Co., Ltd., a member of the Dispute Resolution Co., Ltd., a member of the Dispute Resolution Co., Ltd., a member of the Dispute Resolution Co., Ltd., a member of the Dispute Resolution Co., Ltd., a member of the Dispute Resolution Co., Ltd., a member of the Enterprise Co.

Accordingly, the defendant acquired property in return for illegal solicitation in relation to his duties.

2. Defendant B

A. From September 2014, the Defendant is a person who works as the representative director of the Steel Production Facility Construction Business Co., Ltd. E from around September 2014 and has overall control over the conclusion, progress, business, etc. of a contract with a trader.

In January 2015, the Defendant made an illegal solicitation to the Plaintiff, the director of the Dispute Resolution D Co., Ltd., to the effect that the Plaintiff would exercise influence on the re-subcontracting construction works from the primary sub-contractor of the Dispute Resolution D Co., Ltd., or that the Dispute Resolution E will change various conveniences in the process of performing the project to award a contract to the Dispute Resolution D Co., Ltd., which he has received a re-subcontracted, and delivered KRW 20,000 to A from January 2015 to December 2016.