Text
1. As to KRW 235,784,482 and KRW 148,284,482 among the Plaintiff, the Defendant shall pay to the Plaintiff KRW 235,784,482 from November 14, 2018 to December 18, 2019.
Reasons
1. The plaintiff's assertion
A. On February 13, 2018, the Plaintiff: (a) received a household installment loan of KRW 150,000,000 from C Bank; and (b) lent the loan to the Defendant (hereinafter “instant first loan”); (c) the Defendant agreed to repay the principal and interest of the loan on behalf of the Plaintiff on behalf of the Plaintiff; and (d) additionally pay KRW 100,000 per month to the Plaintiff as interest.
However, the Defendant did not pay three-month interest (from July 12, 2018 to October 12, 2018) among the interest that the Defendant paid to the Plaintiff only the principal and interest on the said loan until November 13, 2018.
Therefore, the Defendant is obligated to pay to the Plaintiff the unpaid principal of KRW 148,584,482 (i.e., the unpaid principal of KRW 148,284,482 plus KRW 300,000) and damages for delay from October 13, 2018.
B. The Plaintiff leased KRW 20,500,000 to the Defendant on March 22, 2018, including KRW 5,500,000, and KRW 20,500,000 on March 24, 2018, and KRW 120,000 per month without setting the due date for repayment.
(2) The Defendant is obligated to pay the Plaintiff damages for delay as of August 24, 2018. The Defendant paid only the interest for five months (from March 24, 2018 to August 23, 2018) with respect to the above loan. The Defendant is obligated to pay the Plaintiff KRW 20,500,000 and the damages for delay from August 24, 2018.
C. On October 22, 2018, the Plaintiff received a loan from D and E, and lent KRW 64,000,000 to the Defendant (hereinafter “instant third loan”). The Defendant agreed to repay 5.5% per month, which is the parties to each of the above loans, on behalf of the Plaintiff.
However, the defendant does not repay interest on the above loan. The defendant is obligated to pay to the plaintiff 64 million won and delay damages from October 22, 2018.
The plaintiff shall claim the return of the loan of KRW 5,00,000.