(영문) 서울중앙지방법원 2021.01.20 2020가합566445
양수금
Text

1. As to the Plaintiff’s KRW 258,589,229 and its KRW 157,00,000 among them, the Defendant shall start from February 15, 2020 to July 6, 2020.

Reasons

Provided, That the Korea Trade Commission set the interest rate of KRW 7.10 per annum on January 21, 2010; KRW 76,000,000 per annum on September 27, 2012; and leases KRW 6.91 per annum on September 27, 2012; the Korea Trade Commission transferred each of the above loans to the Plaintiff on November 28, 2018; and C Trade Association, on July 1, 2019; it notified the Plaintiff of the transfer of each bond; the Defendant of the transfer of each of the above loans on January 21, 2010; the Defendant was unable to reach a dispute on the principal amount from July 17, 2018; KRW 30,000 per annum on September 29, 2012; and the Defendant lost the interest rate of KRW 30,000 per annum from July 25, 2018; and each of the parties’ interest in arrears from September 29, 2018.2

Comprehensively taking account of the above facts, the Defendant is obligated to pay the Plaintiff damages calculated by the annual interest rate of 7.10% per annum from February 15, 2020 to July 6, 2020, for the amount of KRW 258,589,229 and the amount of KRW 157,00,000,00 from the date of delivery of a copy of the complaint of this case from February 15, 2020, for the amount of KRW 12% per annum under the Act on Special Cases concerning the Promotion, etc. of Legal Proceedings, for the amount of KRW 76,00,000 from the next day to the date of full payment, to the day of full payment, from February 15, 2020 to July 6, 2020; and for the amount of KRW 6.91% per annum from the next day to the date of full payment.

2. It is so decided as per Disposition by the assent of all participating Justices, on the ground that the plaintiff's claim of this case is reasonable.