(영문) 인천지방법원 2015.05.22 2015가단6653
공사대금
Text

1. The Defendant shall pay to the Plaintiff KRW 36,535,950 as well as 20% per annum from January 7, 2015 to the day of complete payment.

Reasons

1. Facts recognized;

A. The Plaintiff, who received from the Defendant, a payment of KRW 34,511,950 from the Defendant for the Cump prevention work, and completed on May 15, 2014.

B. In addition, on July 21, 2014 at the Defendant’s request, the Plaintiff supplied materials equivalent to KRW 2,024,000 related to the Works for the Prevention of Oil Pollution in Nam-gu Incheon Metropolitan City.

[Ground of recognition] Facts without dispute, entry of Gap evidence 1 to 8 (including a provisional number), the purport of the whole pleadings

2. According to the above facts of recognition as to the cause of the claim, barring any special circumstance, the Defendant is obligated to pay to the Plaintiff 36,535,950 won in total, and damages for delay calculated at the rate of 20% per annum from January 7, 2015 to the day of complete payment, which is the day following the delivery of the original copy of the instant payment order, to the day of full payment.

3. In conclusion, the plaintiff's claim of this case is reasonable and thus the plaintiff's winning judgment is pronounced.