logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울서부지방법원 2017.06.29 2016가합1830
추심금
Text

1. The Defendant’s KRW 103,140,400 as well as 6% per annum from April 27, 2016 to June 29, 2017 to the Plaintiff.

Reasons

1. Facts of recognition;

A. Construction contract 1) The Defendant is a land building corporation on January 19, 2015 (hereinafter “branch building”) and the Defendant.

B) As to the civil engineering works among the “new construction works” in the “B-New Construction Works,” the Defendant entered into a subcontract agreement between January 19, 2015 to May 31, 2016, with the construction period of KRW 8,600,000,00. 2) On June 3, 2015, the lower court concluded a subcontract modification agreement (including the modification agreement) that increases the construction price of KRW 8,749,325,00, and KRW 8,808,215,00 on November 20, 2015.

3) On December 3, 2015, the instant construction contract was rescinded with the Defendant on December 3, 2015, and on the same day, the instant construction contract was rescinded. The main contents of the instant construction contract are as follows: 8,808,215,00 won (including purchase tax and taxation) contract date of 19 January 19, 2015; 06,000 won for the above contract date; 06,00 won for the remaining construction after December 03, 2015; 06,00 won for the first 60,00 won for the construction work; 06,00 won for the construction work; 80,00 won for the first 60,000 won for the construction work; 80,50,000 won for the construction work after December 03, 2015; 96,06,000 won for the construction work price for the first 60,085,0800 won for the construction work price for the following 806.

B. The Plaintiff’s claim for the payment of the instant construction price is the claim for the amount of KRW 648,754,685, which the Plaintiff had against the land purchase.

arrow