Text
1. The plaintiff's claim is dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
Reasons
(c) Use the loan granted by the contractor for the partnership and pay the bid bond in cash;
(2) A tender bond deposited by a participating executor shall be converted to a loan immediately when selecting a successful bidder with respect to the remaining amount, excluding KRW 150,000,000,00 for public relations and public relations, joint publicity, and expected expenses related to the general meeting, and shall be lent within 15 days from the date of requesting the cooperative to provide additional funds for service costs, etc.
Article 17 (Duties of Successful Bidders) (1) A successful bidder shall conclude a contract in consultation with the ordering person within three months from the date on which the ordering person notifies the general meeting of selecting the contractor.
Provided, That the period may be extended by consultation between the project owner and the successful bidder in extenuating circumstances.
(2) A successful tenderer shall faithfully comply with a request by an project owner to conduct business necessary for the promotion of a project even before concluding a construction contract.
[Business Proposal of this case] * 16 special benefits (4 pages of the above proposal) 16 (2) finalized construction cost without any change in construction cost due to geological conditions. 8 Payment of KRW 10,000,000 for directors’ expenses (payment of KRW 5,000,000 after the selection of the contractor for the work, and KRW 5,000,000 after the conclusion of the provisional contract): It is difficult to immediately pay KRW 5,000 within one month after the selection of the contractor for the thickness of the entire union members, and the additional KRW 5,00,000 shall be paid without compensation within one month after the execution of the provisional contract.
* Business Participation Conditions
4. Construction cost - Method of business participation: Contract construction cost - Contract construction cost: 3,599,000 won / base time for calculating construction cost - Construction cost - Construction period as of June 2012: 32 months from the commencement date of construction: Final construction cost (no increase in construction cost is made until the base date for calculating construction cost, no increase in construction cost after the commencement of construction): Members' expenses for directors;
B. As seen above, the Plaintiff was selected as the developer of the instant redevelopment project, around September 2010.