1. On August 27, 2012, the Defendant: (a) on each real estate listed in the separate sheet to the Plaintiff, the Daegu District Court Branch Branch of Port Branch of the District Court.

Reasons

1. Basic facts

A. On March 22, 1995, Han-dong Co., Ltd. (1) The construction process of each of the instant real estate and the process of the registration of ownership preservation) Han-dong Co., Ltd. (hereinafter “instant site”) shall be 4,072m25m2.5m2 (hereinafter “instant site”).

purchase of the same year;

8. The registration of ownership transfer was completed on 16.16. Around that time, the construction of each real estate listed in the separate sheet (hereinafter “each of the instant real estate”) was suspended due to a default on the construction of reinforced concrete structure from the first to fifth above ground, after obtaining approval for a project plan to build an apartment building with the 15th above ground level on the instant site from Port-si.

2) On April 18, 2003, the Plaintiff purchased the instant building site and the instant real estate construction business license and revised the housing construction project plan from the port of port to the Plaintiff for the alteration of the housing construction project plan from the port of port to the Plaintiff, and had the Plaintiff resumeed the construction work, and suspended the construction work on or around May 2005 due to the sale rate low. 3) The Plaintiff and the Plaintiff’s representative director, the Plaintiff, and the Plaintiff’s representative director, the amount of 90% for the instant real estate and the instant land related to the instant real estate for which the structural construction was completed to the F Co., Ltd., Ltd. (hereinafter “F”) at the time, to the extent of 90% at the time:

B.1. As described in paragraph 1. The rights were transferred to the Defendant and G.

(2) The transfer contract of this case was agreed upon as follows (hereinafter “instant transfer contract”).

1.1. E shall be the co-representative of the F.

2. H was appointed as the representative director of the F on September 3, 201, and on September 11, 2012, H was dismissed from the representative director on February 14, 2013 after the Ulsan District Court received a provisional disposition suspending the performance of its duties. H transfers 55% of the F’s shares to E.

3. The proprietor of the Port shall be changed from the present time to the F.

4.The total purchase price of a building shall be 2.15 billion won, shall be 1.2 billion won with the PF funds, and any balance shall be paid after completion.

5. E shall be total.