(영문) 광주지방법원 2015.01.29 2014가합3018
공사대금
Text

1. The Defendant shall pay to the Plaintiff KRW 251,827,766 as well as 20% per annum from January 3, 2015 to the day of full payment.

Reasons

1. Basic facts

A. On December 27, 2012, the Plaintiff entered into a contract with the Defendant for a construction project under a provisional name A (hereinafter “instant construction project”) (hereinafter “instant construction project”) with respect to the contract amount of KRW 7,488,274,00, and the commencement date of the project, January 3, 2013, and January 27, 2014 as of the completion date (hereinafter “instant construction contract”).

After that, on January 27, 2014, the instant construction was finally changed on several occasions, and the contract amount was changed to KRW 7,708,269,000 on February 21, 2014.

B. On the other hand, on February 25, 2013, the Plaintiff entered into a subcontract for construction works with respect to reinforced concrete construction (hereinafter “instant subcontracted construction”) among the instant construction works (hereinafter “instant subcontracted construction”) at the cost of KRW 1,430,75,373 from February 25, 2013 to January 31, 2014 during the construction contract period (hereinafter “instant subcontract”).

C. On March 18, 2013, the Plaintiff and Mawon case drafted a written consent to the direct payment of the subcontract price in this case to Mawon case. D.

1. Of the progress of the instant construction, the following 201: 3.1: 2013Kadan4521 B; 19.7. 193,313; 2013Kadan47 C; 54,045, 400 3203Kada4896 D claims; 30. 30. 1. 203. 36. 203. 1. 36. 204. 1. 1. 1. 1. 1. 36. 1. 1. 36. 205 . 3. 1. 1. 36. 204 . 3. 1. 1. 1. 205 . 3. 1. 1. 36. 204 . 3. 3. 1. 1. 1. 1. 2013 . 6. 19,0005 G 20138 . 37 3. 2. . 201. 31. 3. 2. 34. 1. 1. 1. 3