Text
1. All of the plaintiffs' claims are dismissed.
2. The costs of lawsuit are assessed against the plaintiffs.
Reasons
1. Facts of recognition;
A. The building listed in Paragraph 1 of the attached Table, which is the H heading of the G building located outside of the Seoul Jung-gu, Seoul, and eight parcels (hereinafter “First Building”) is owned by the Plaintiff, and the building listed in Paragraph 2 of the attached Table, which is the I heading of the said G building (hereinafter “Second Building”) is owned by the Plaintiffs respectively.
B. On January 2014, the Plaintiffs leased 1 and 2 buildings to the J Co., Ltd. (hereinafter “J”) as follows.
A, building A, B,00,000,000 2,960,000 2,966,000,256,000 3,256,00 from January 16, 2014 to January 15, 2019, building A, B,160,000,000 7,000,000,000,700,700,700,000
C. On July 18, 2014, J, with the consent of the plaintiffs on July 18, 2014, set forth the second building to Defendant E as 80,000,000 won for sublease deposit, monthly rent of KRW 4,400,00 (including value-added tax, and payment in advance on September 4, 2014) and the sublease period from July 25, 2014 to July 24, 2019.
J, with the consent of the Plaintiff, etc., on December 30, 2014, sub-leaseed Defendant C Co., Ltd. (hereinafter “Defendant C”) for the period from December 30, 2014 to December 29, 2019 with the fixed lease deposit amount of KRW 370,00,00,00 for sublease deposit of 370,000,000 for sublease deposit of the above G building and the above G building, (including value-added tax, first-paid payment each month), and the sub-lease period of KRW 26,963,112 (including value-added tax, first-paid payment each month), and the lease deposit amount of KRW 130,00,000,000 for the above G building, and KRW 6,000,000 for the month from January 30, 2015 to KRW 20,010 for the lease period of KRW 201 to KRW 25,2019.
(The sum of the foregoing sub-loans and the leases is referred to as "loans" for convenience. (e)
Since J did not pay the rent for the buildings Nos. 1 and 2, the Plaintiffs filed a lawsuit against J (Seoul Central District Court 2015 Gohap582146) seeking the payment of unpaid rent, and the said court has decided on June 16, 2016 as to the building No. 1.