logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 대전지방법원 2016.06.07 2015나4892
양수금
Text

1. Of the judgment of the court of first instance, the part against the Defendants exceeding the money ordered to be paid under the following subparagraphs shall be revoked.

Reasons

A. In full view of the fact that there is an agreement to pay only KRW 150 million as down payment, it is reasonable to interpret the above receipt stipulation to the effect that the construction price shall be reduced by 25 million among the construction price.

Therefore, the construction cost under the instant construction contract is recognized as KRW 485,00,000.

The 7th parallel 6 to 7th parallel 20 parallels are as follows:

As a result of the fact-finding conducted by the appraiser H of the first instance court, the following circumstances, i.e., the “ROM, wards, kitchens, entrances, and entrances of the instant building,” among the design drawings of the instant building, are designed to close down to remote areas. Part of the design drawings of the instant building was modified and constructed for other days; ② Construction of hallwayl (300*60), toilets, and kitchens (20*400), etc. of the instant construction contract under Article 14 of the Special Conditions of the instant construction contract, provides that “No one shall be constructed for the main room and bathing room in the special construction contract, but only for the main room, other than the main room, other than the main room, other than the main room, other than the main room.” The Plaintiff’s additional part of the instant construction contract is clearly distinguishable from the main room and the main room, and the Plaintiff’s additional part of the instant construction contract, see the Plaintiff’s explanation and supplementary part of the instant construction project.”

arrow