(영문) 대전지방법원 2019.10.24 2019가단108371
공사대금
Text

1. The Defendant’s KRW 60,500,000 as well as its annual 6% from February 27, 2019 to August 13, 2019 to the Plaintiff.

Reasons

1. The description of the grounds for the claim shall be as specified in the attached Form;

2. Judgment without any ground (Articles 208 (3) 1 and 257 of the Civil Procedure Act);

3. The statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases concerning the Promotion, etc. of Partial Dismissal Lawsuit is recognized as being amended on May 21, 2019 and enforced on June 1, 2019, only the damages for delay calculated at the rate of 12% per annum from the day following the delivery date of a copy of the complaint of this case to the day of complete payment, and the exceeding portion shall be dismissed.