(영문) 서울중앙지방법원 2015.10.08 2015가합503143
공사대금
Text

1. The Defendant’s KRW 120,000,000 as well as 6% per annum from July 2, 2014 to January 29, 2015 to the Plaintiff.

Reasons

1. Basic facts

A. On October 22, 2013, the Defendant concluded a contract between the Plaintiff and the Defendant, setting the construction period between October 22, 2013 and April 22, 2014, the contract period of KRW 330,000 for the construction of multi-family housing in Gwangjin-gu Seoul Special Metropolitan City (hereinafter “instant construction”) to the Plaintiff (hereinafter “instant contract”). The main contents of the instant contract are as follows.

Construction Management Service Contract

1. Construction name: New construction of multi-household housing;

2. Location: Gwangjin-gu Seoul;

5. The ordering person and the manager of other matters shall enter into a contract for services with contractual documents attached thereto on an equal footing with each other, and promise to perform the contractual obligations in good faith and sincerity, and shall prepare a contract as evidence and keep one copy of the contract in custody of each of the parties concerned:

Attachment:

1. One copy of the contract terms of the construction management service;

2. The terms and conditions of the design drawing management services terms and conditions set forth in Article 1 (General Provisions) of the terms and conditions of the contract shall be provided by the Corporation Manager (hereinafter referred to as “B”) for the smooth performance of the project with respect to the new construction project in progress by the project owner (hereinafter referred to as “A”), and shall determine the rights and obligations between the parties to the contract.

Article 8 (Methods of Payment of Construction Costs)

1. Where Party A wishes to pay the construction price directly to Party B, he/she shall cooperate in the method and procedure for such payment, unless there is any special reason;

The remaining completion amount of 120,000,000 progress payment for the portion of 90,000,000 progress payment for the portion of 120,000,000 progress payment for the remaining completion within 15 days after completion of 10,000,000,000

2. The timing and amount of payment shall be determined in consultation with A and B as follows:

Article 13 (Special Conditions)

1.Except as otherwise provided for in this Agreement, a separate special agreement may be made by mutual agreement between A and B.