logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울중앙지방법원 2016.08.25 2016가단5078871
대여금
Text

1. The Defendant’s KRW 41,876,44 and KRW 27,759,58 among the Plaintiff’s KRW 23.5% per annum from April 8, 2016 to the date of full payment.

Reasons

According to the purport of each of the statements and arguments in Gap evidence Nos. 1 through 7, it is acknowledged that the defendant has the same facts as the reasons for the claim. The defendant is obligated to pay to the plaintiff the amount of delay damages calculated at the rate of 24.7% per annum, which is the overdue interest rate of 23.9% per annum from April 8, 2016, the following day after the base date of the above claim, as to the principal of the KB Card and the overdue interest of KRW 27,759,58 as of April 7, 2016, and the total amount of the overdue interest of KRW 41,876,44 as of April 7, 2016, which is the base date of claim No. 11,573,681, which is the repayment principal of the card transfer interest, from April 8, 2016 to the day of complete payment.

I would like to say.

Therefore, the plaintiff's claim of this case is reasonable, and it is decided as per Disposition by admitting it.

arrow