logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 청주지방법원 2020.04.08 2019가합705
공사대금
Text

1. The Defendant’s KRW 478,500,000 as well as 5% per annum from July 1, 2017 to December 9, 2019, respectively, to the Plaintiff.

Reasons

1. Basic facts

A. On January 1, 2017, the Plaintiff entered into a contract on reinforced concrete and civil engineering works (hereinafter “instant contract”) among the construction works of factories on nine parcels, other than the Seoul, Seo-gu, Chungcheongnam-gu, Chungcheongnam-gu, and the main contents thereof are as follows.

Standard contract for private construction works

4. Date scheduled for completion: The contract amount of the construction project on June 30, 2017: KRW 478,500,000 (including surtax).

6. Prepaid money: 191,400,000 won (including surtax);

7. Completion portion: 191,400,000 won (including surtax).

8. Completion money: 95,700,000 won (including surtax, after completion payment).

B. The Plaintiff completed the construction on June 30, 2017, which was due date for completion.

[Ground of recognition] Facts without dispute, Gap evidence Nos. 1, 2, and 3, the purport of the whole pleadings

2. According to the above facts of recognition, the Plaintiff completed the construction on June 30, 2017, which is the deadline for completion. As such, the Defendant is obligated to pay the Plaintiff the unpaid construction cost of KRW 478,50,000 and the damages for delay at each rate of KRW 5% per annum under the Civil Act from July 1, 2017 to December 9, 2019, which is the date of delivery of a copy of the complaint of this case, as sought by the Plaintiff, from July 1, 2017 to December 9, 2019, as claimed by the Plaintiff.

3. In conclusion, the plaintiff's claim is reasonable, and it is so decided as per Disposition.

arrow